Home » Case Studies » Leicester Schools Project with Portakabin

Leicester Schools Project

In May 2017, Leicester City Council (LCC) announced plans to work on the next phase of a multi-million pound expansion programme to provide thousands of new pupil places in Leicester.

In total, LCC has invested £11.5m in providing interim classroom buildings for seven primary and six secondary schools.

Offsite construction specialist Portakabin was appointed to provide classroom space for the six secondary schools. As part of the project, Tecserv UK was sub-contracted to install fire safety and security systems to ensure the buildings and occupants were protected from fire and other security risks.

*Photo courtesy of Portakabin.

Want to work with us?

The challenge

Tecserv UK was given the brief for the project in May 2017, and once the approval to proceed was granted in July, the project to install the temporary accommodation had to be completed within a very tight timescale. This was because the buildings had to be ready to open in time for the new school year which began in Leicester at the end of August 2017.

Tecserv UK was appointed to install fire safety and security systems within the Portakabin buildings at six schools. These schools had been identified as being in immediate need of classrooms in order to meet the demands for school places in the new academic year.

The solution

Working across six school sites, the project involved the installation of Gent fire alarm systems, Paxton Net2 access control systems, Castle intruder alarms and Hikvision CCTV systems at the following schools: Babbington Community College, Crown Hills, City of Leicester, Soar Valley Rushey Mead Academy and Judgemeadow.

The buildings comprised 45 standard classrooms, nine science classrooms, three design and technology classrooms, an expressive arts studio, an art studio, multi-use spaces, toilets, changing rooms and showers, staff rooms and dining rooms.

The tight timescale meant that there were a number of challenges that only came to light as the project progressed. The Tecserv installation team liaised very closely with the Portakabin project team and other contractors to ensure all works were co-ordinated and scheduled efficiently to meet the project deadline.

 

The outcome

The project was subsequently entered into and won the 2018 East Midlands Celebrating Construction Awards in the ‘Offsite Project of the Year’ category.

Quote

We have worked with Tecserv UK on a number of projects, often with a tight deadline, so we were confident the team would be capable of delivering the specialist safety and security systems required in time for the start of term.

Sarah Jane Field Business Manager for Portakabin

Want to work with us?

Here are some past projects we’ve worked on

Speak to us about fire & security system installation & maintenance

Please note Tecserv UK only operate within the United Kingdom – any work outside of this region cannot be considered.

We’re fully accredited